World Bank · Engineering design
Heating design and tender documentation for Kherson
Preparation of design and tender documentation for district heating modernisation. The scope covered 15 boiler plants, 13 individual heat substations and 8,816 metres of heat networks.
Schematic illustration of the engineering scope.
- Period
- December 2017 — May 2019
- Funding
- IBRD / World Bank, UDHEEP
- KES’s role
- Documentation prepared in consortium with COWI.
KhersonThe task and
The task and
engineering context
An engineering basis for subsequent procurement and implementation within the agreed design contract.
This case concerns design and tender documentation. The listed facilities are not a claim that KES constructed them.
Scope of works
- Documentation for 15 boiler plants.
- Documentation for 13 individual heat substations.
- Heat network design scope of 8,816 metres.
Figures are based on company materials and the ReBuild presentation dated 21 October 2026. Scope and role are stated for each project.