GIZ programme · 2025
13 modular boiler units for Ukrainian communities
A decentralised heat supply programme: 13 modular boiler units with a combined thermal capacity of 38 MW at 11 addresses.

- Period
- February — June 2025
- Funding
- GIZ programme
- KES’s role
- Delivery of modular boiler works within the contracted programme.
7 locations in UkraineThe task and
The task and
engineering context
The portfolio combines facilities of different uses and capacities, demonstrating coordination of supply and works across several communities within one programme.
38 MW refers to this programme only. Thirteen boiler units do not mean thirteen separate addresses.
Scope of works
- 13 boiler units at 11 addresses; one site may accommodate several modules.
- Combined programme thermal capacity: 38 MW.
- Locations: Pavlohrad, Lozova, Lymanivka, Myrhorod, Kremenchuk, Sumy and Shostka.
Figures are based on company materials and the ReBuild presentation dated 21 October 2026. Scope and role are stated for each project.